Display the calendar for jobs not scheduled in CA-7.
Posted: Tue Sep 30, 2014 4:47 pm
by Avadhesh Tiwari
Hi,
I came to know that every Job defined in CA7 may not be a scheduled Job, if it is not a scheduled Job how can I check that when a particular job will get executed?
Thanks for your help.
Re: Display the calendar for jobs not scheduled in CA-7.
Posted: Tue Sep 30, 2014 5:33 pm
by Robert Sample
Jobs can be triggered via date / time in CA-7, but they can also be triggered by the completion (or failure) of another job, or even by the creation of a data set on the system. In the latter two cases, there is no schedule for them since CA-7 doesn't consider them to be calendar-based.
Re: Display the calendar for jobs not scheduled in CA-7.
Posted: Wed Oct 01, 2014 11:37 am
by Avadhesh Tiwari
Thanks Robert. Then for such job how can I see their scheduling pattern?
Re: Display the calendar for jobs not scheduled in CA-7.
Posted: Wed Oct 01, 2014 5:24 pm
by Robert Sample
I don't know of a general way (but then I am not a CA-7 expert). If you list the individual job, you can see how it is triggered.